CONSTRUCTION SCHEDULE

ACTIVE  AREAS

Screenshot 2025-05-07 at 4.42.10 PM.png
39th Avenue, Greenway Road - Paradise Lane

Sewer rehabilitation work begins May 21

Street restoration work anticipated in August 2025

Area

Location

Progress

Area # IV-05

39th Avenue, Acoma Drive - Thunderbird Road

IV-05

MAY 21 - AUG. 1, 2025

IV-06

Area # IV-06

39th Avenue - Cactus Road         

NOT YET SCHEDULED

Area # IV-09

39th Avenue, Peoria Avenue - Butler Drive        

IV-09

NOT YET SCHEDULED

IV-07

Area # IV-07

43rd Avenue - Grand Avenue

NOT YET SCHEDULED

IV-11

Area # IV-11

43rd Avenue - Northern Avenue

NOT YET SCHEDULED

IV-12

Area # IV-12

75th Avenue, Encanto Blvd - Roosevelt Street

COMPLETED

Area # IV-13

Colter Street - 15th Avenue

NOT YET SCHEDULED

IV-13
IV-14

Area # IV-14

67th Avenue - Garfield Street

NOT YET SCHEDULED

III-01

Area # III-01

I-10 - 47th Avenue

NOT YET SCHEDULED